Project investment process in industrial park
Step 1: Prepare for project investment
The first point of note when investors choose a major industrial park is to prepare a full legal record including:
– Business registration
– Registering investment in industrial parks
– Signing a contract on land lease principles
See details of the process of preparing investment projects in the industrial park at: Preparing to invest in projects in industrial parks
Step 2: Please invest
Carry out the procedure for applying for investment registration certificates (investment policies). The implementing subjects are domestic investors and economic organizations specified in Clause 2, Article 23 of the Investment Law 2014 must apply for investment policy decisions when investment projects are subject to the decision on investment policy specified in Article 30, Articles 31 and 32 of the Investment Law.
View details of the order and application for investment policy at: The stage of applying for investment policy of industrial parks
Step 3: The process of land allocation and lease in an industrial park
Understanding the process of allocating or renting land for investment projects in Vietnam will help investors be proactive in implementing. The land lease process consists of the following specific steps:
– Signing an official land lease contract
– Handing over the premises
– Issuance of certificates of QSDD
Detailed process viewed at: Process of allocation and lease of land for investment in projects in industrial parks
Step 4: Approve the total area (planning) of the project in the industrial park
– Selection of design consultants – firefighting consultants
– Survey of the status quo
– Making and approving the total premises
Guidance on procedures and order of implementation of approval of total premises (planning) at:
Step 5: Design – approve the basic design
Agency receiving the basic design: Management board of industrial parks. This phase is implemented with the following 4 basic steps:
– Making and approving environmental impact assessment reports – EIA
– Preparation and approval of firefighting design
– Preparation – appraisal of the basic design
– Making and approving technical design and estimating
The sequence of detailed steps can be implemented at: ….
Step 6: Apply for a building permit
– Apply for a construction permit printed with construction permit
– Completion of infrastructure connection procedures
Steps taken, application for construction permits please see details at:
Step 7: Construction and installation
– Bidding, selection of construction contractors
– Organizing the implementation of construction and installation of works
The construction must comply with the approved ground planning and technical design. Detailed construction and installation process at:
Step 8: Acceptance completes the work and put it into use
– Firefighting acceptance
– Completed
– Acceptance of completion of works and put into use
– The assignment of property on the land
Detailed contents of the acceptance work to complete the work put into use here.